- Status
- Approved by right (Technology Overlay District); under development
- Developer / parties
- Amazon Web Services
- Location
- Louisa County
- Size
- Lake Anna campus about 150 acres next to North Anna Power Station; North Creek campus on parts of a 1,444-acre tract south of Route 33 (Engage Louisa newsletter; the county document says the by-right campuses total about 2,300 acres)
- Investment
- $11 billion announced Aug 2023 for two campuses (Louisa County document)
- Reported benefits
- County estimates new revenues could exceed $25 million a year at $11B investment; 'several hundred' jobs likely (Louisa County document; county estimates, not verified)
- Concerns / impacts
- The campuses use raw (untreated) reservoir water for cooling from Northeast Creek Reservoir, safe yield 3.2 million gallons per day (Louisa County document)
- Last verified
- 2026-11-02
Milestones
- Apr 2023 Technology Overlay District adopted
- Aug 2023 AWS announced $11B for two campuses
- Aug 2024 Board reduced the overlay and required a CUP for any new data center
- county expects raw-water delivery to the Lake Anna campus by Jan 2027
- projected 15-year build-out (Louisa County document)
Related records
Sources
- Official record louisacounty.gov
- News report tammypurcell.substack.com
Free weekly digest
Email digest: not open yet
The free weekly email digest is not accepting signups yet, and we collect no email addresses on this site. Every locality and project page is free to read now.
Want it same-day? Neighbor, $4/mo.