Data centers in Prince William County, Virginia: a source-linked guide

13 projects · 38 dated records · last verified 2026-11-02. Built only from records we have opened; every fact links to its source.

Live tracker: projects and dated records for Prince William County. This page is the long-form guide.

At a glance

Projects tracked
13 (8 proposed / announced, 4 denied / withdrawn / canceled, 1 approved / permitted)
Dated records
38 (12 DEQ air permit; 9 Board of Supervisors; 8 County planning; 6 Court ruling; 1 Utility regulator (SCC); 1 Community; 1 State action)
Official-source records
25 of 38
Last verified
2026-11-02

Projects in Prince William County

PW Digital Gateway (Compass / QTS)

Canceled (rezonings voided; developer terminated project)

Developer (as stated)
QTS and Compass (developers, per InsideNoVa/WTOP)
Location
Gainesville area
Size (as stated)
Proposed: over 22 million sq ft of data centers on about 2,000 acres along Pageland Lane, next to Manassas National Battlefield Park (per InsideNoVa/WTOP)
Sources
2 linked (News report) · last verified 2026-11-02
  • Dec 2023 Board of County Supervisors approved the rezoning (InsideNoVa/WTOP)
  • Aug 2025 Prince William Circuit Court ruled the rezonings void for improper public notice (InsideNoVa/WTOP says 'last August')
  • Mar 31 2026 Court of Appeals upheld that ruling

Dulles South Innovation Center / Dulles Cloud South

Comprehensive plan amendment denied 8-0 (Jul 7, 2026)

Developer (as stated)
Sanders Lage Assemblage I LLC (comprehensive plan amendment requestor, per InsideNoVa/WTOP)
Location
Gainesville District (Sanders Lane)
Size (as stated)
Proposed: 43 million sq ft of data centers on about 1,940 acres (about 252 parcels) near the Loudoun County border (InsideNoVa/WTOP)
Sources
2 linked (News report) · last verified 2026-11-02
  • Jul 7 2026 Board of County Supervisors voted 8-0 to deny a comprehensive plan amendment (AF agriculture/forestry to I-3 industrial and MU-1 mixed-use hamlet) that would have preceded a rezoning from A-1 to PBD
  • staff recommended denial because the site is outside the Data Center Opportunity Zone Overlay District
  • a late deferral request failed 7-1 (InsideNoVa/WTOP)

Project Industry (REZ2025-00003)

Board of Supervisors deferred action (Sept 1, 2026 hearing), pending

Developer (as stated)
Industrial Park Court LLC (applicant per county staff report)
Location
Prince William County
Size (as stated)
Proposed: two data center buildings (staff report) on 42.28 acres at up to 0.35 FAR, 85 ft height including rooftop equipment (DAPS), substation up to 300 MW and 110 ft height
Sources
2 linked (Official record) · last verified 2026-11-02
  • Sep 6 2024 application accepted, May 20 2026 Planning Commission motion to deny failed 3-3 and no action was taken, Sep 1 2026 Board hearing date, DAPS lists the case as deferred (Nov 2 2026 report), the county documents describe the Commission outcome both as deemed recommendation for approval (staff report) and deemed approved (draft ordinance language)

Madera Farm data centers (SUP2027-00002), Nokesville

Application under review, no Planning Commission hearing scheduled

Developer (as stated)
Madera Farm applicant (name not confirmed in the sources we opened)
Location
Nokesville
Size (as stated)
Proposed: rezoning of about 228.88 acres to M-1 plus a special use permit for data centers up to 75 ft tall and substations outside the Data Center Opportunity Zone Overlay District (DAPS). Prince William Times reports seven data centers
Sources
3 linked (News report, Official record) · last verified 2026-11-02
  • Oct 30 2024 rezoning application accepted and Jul 31 2026 special use permit application accepted (DAPS), residents raised concerns about seven data centers in Nokesville (Prince William Times)

Atlantic Funding Development data centers (Dumfries Road)

Staff comments issued Sep 16, 2026, applicant has 45 days to revise, no Planning Commission hearing scheduled

Developer (as stated)
Atlantic Funding LLC (per Potomac Local, summarizing InsideNoVa)
Location
Dumfries Road, near Four Seasons
Size (as stated)
Proposed: about 60 acres, three data center buildings and a substation (DAPS, Potomac Local), building height up to 75 ft
Sources
2 linked (News report, Official record) · last verified 2026-11-02
  • May 22 2026 rezoning and May 26 2026 special use permit applications accepted (DAPS), Sep 16 2026 staff found substantial issues and gave 45 days to revise (Potomac Local)

Southgate South data centers

Staff comments issued Sep 16, 2026, applicant has 45 days to revise, no Planning Commission hearing scheduled

Developer (as stated)
Southgate Business LLC (per Potomac Local, summarizing InsideNoVa)
Location
Dumfries Road, near Four Seasons
Size (as stated)
Proposed: about 79 acres, three data center buildings and a substation (DAPS, Potomac Local), building height up to 65 ft
Sources
2 linked (News report, Official record) · last verified 2026-11-02
  • Jun 3 2026 rezoning and special use permit applications accepted (DAPS), Sep 16 2026 staff found substantial issues and gave 45 days to revise (Potomac Local)

Gardner Property data centers (REZ2023-00018, SUP2027-00008)

Rezoning and special use permit under review, no hearing scheduled

Developer (as stated)
Not named in the sources we opened
Location
Prince William County
Size (as stated)
Proposed: 82.74 acres with data centers and a substation, building height up to 66 ft plus rooftop equipment to 81 ft (DAPS)
Sources
1 linked (Official record) · last verified 2026-11-02
  • Mar 22 2023 rezoning accepted (DAPS), Sep 24 2026 a special use permit application was filed (DAPS)

University Business Park data centers (REZ2023-00019)

Rezoning under review, no hearing scheduled

Developer (as stated)
Not named in the sources we opened
Location
Prince William County
Size (as stated)
Proposed: 117.28 acres at M-1 with proffers, up to 3.8 million sq ft with a new substation (DAPS)
Sources
1 linked (Official record) · last verified 2026-11-02
  • Mar 30 2023 application accepted (DAPS), still pending in the Nov 2 2026 DAPS report

Ashton Data Center (REZ2022-00031)

Planning Commission recommended denial (Jun 26, 2024), Board has not heard the case

Developer (as stated)
Not named in the sources we opened
Location
Prince William County
Size (as stated)
Proposed: 51.85 acres, agricultural and R-6 to M/T, building height up to 110 ft (DAPS)
Sources
1 linked (Official record) · last verified 2026-11-02
  • Aug 30 2022 application accepted, Jun 26 2024 Planning Commission recommended denial, Board hearing listed as not heard (DAPS)

NOVEC Diamond Hill Substation (PFR2026-00005)

Planning Commission denied 5-3 (Mar 11, 2026), InsideNoVa headline says it was sent back to the Planning Commission (details unverified)

Developer (as stated)
Northern Virginia Electric Cooperative (NOVEC)
Location
Prince William County
Size (as stated)
Proposed 300-megawatt substation (InsideNoVa headline)
Sources
3 linked (News report, Official record) · last verified 2026-11-02
  • Sep 10 2025 application accepted, Mar 11 2026 Planning Commission voted 5-3 to deny (DAPS), InsideNoVa headline says the substation was sent back to the Planning Commission, the article text could not be opened so reasons are unverified

Dominion Vint Hill substation expansion (SUP2025-00009), Prince William

Denied by the Board of Supervisors (Sep 22, 2026), Dominion filed suit Oct 22, 2026

Developer (as stated)
Dominion Energy Virginia
Location
Prince William County (Brentsville area)
Size (as stated)
Proposed: 23.41 acres, 500 kV equipment (DAPS, Prince William Times)
Sources
3 linked (News report, Official record) · last verified 2026-11-02
  • Sep 16 2024 application accepted, Oct 29 2025 Planning Commission took no action, Sep 22 2026 Board denied the special use permit, Oct 22 2026 Dominion filed suit in Prince William Circuit Court (DAPS and existing records)

Devlin Technology Park (Amazon), Bristow

Approved by the Board of Supervisors (Nov 28, 2023), rezoning upheld by the Court of Appeals (Sep 16, 2025), Amazon closed land purchase Nov 5, 2025

Developer (as stated)
Stanley Martin Homes (seller), Amazon Data Services (buyer)
Location
Bristow (Devlin and Linton Hall roads)
Size (as stated)
270-acre park, zoning allows up to about 3.5 million sq ft of data center use (Virginia Business, court opinion). Prince William Times reported nine data centers, so capacity descriptions differ
Investment (as stated)
Amazon paid about $700 million for about 188.5 acres (Virginia Business)
Sources
4 linked (News report, Official record) · last verified 2026-11-02
  • Nov 28 2023 Board rezoned to M-2 and added the park to the Data Center Opportunity Zone Overlay District after a 12-hour hearing (court opinion, Prince William Times), Sep 16 2025 Court of Appeals affirmed dismissal of the neighbors' challenge, Nov 5 2025 Amazon Data Services closed on about 188.5 acres from Stanley Martin Homes

Dominion Morrisville-Wishing Star 500 kV transmission line (SCC PUR-2026-00021)

Under State Corporation Commission review, evidentiary hearing begins Nov 16, 2026

Developer (as stated)
Dominion Energy Virginia
Location
Fauquier, Prince William and Loudoun counties
Size (as stated)
New 500 kV line spanning several counties (Dominion project page). The county page lists about 4.8 miles in Loudoun while United Loudoun says 4.4 miles, so mileage by county is conflicting
Sources
2 linked (News report, Official record) · last verified 2026-11-02
  • Nov 16 2026 SCC evidentiary hearing begins (Dominion project page)

Upcoming hearings and deadlines

2026-11-16
Utility regulator (SCC) News report · Dominion Morrisville-Wishing Star 500 kV transmission line (SCC PUR-2026-00021)

Upcoming: SCC evidentiary hearing begins on Dominion's Morrisville-Wishing Star 500 kV line (PUR-2026-00021), per Dominion's project page.

Source: dominionenergy.com ↗
2026-12-21
Board of Supervisors Official record

Upcoming deadline: under Sec. 32-509.03(2)(e) of Ordinance 26-67, the fifth eligibility criterion requires pending rezonings, special use permits, proffer amendments, substation reviews and site plans to be accepted within 90 days after adoption. Dec 21, 2026 is our calculation (Sept 22 plus 90 days); the county page states '90 days following ordinance adoption'. Confirm the exact date in the ordinance.

Source: pwcva.gov ↗

Timeline of dated records

2026-11-02
County planning Official record

Pending per the Nov 2, 2026 DAPS report: Six Towers Industrial Park (REZ2026-00019, about 23.8 acres at Dumfries and Six Towers roads, up to about 518,649 sq ft of M-2 uses including data centers) and Manassas Corporate Center 8 (REZ2026-00032, about 23.25 acres for a data center). The report lists no hearing dates for either.

Source: eservice.pwcgov.org ↗
2026-11-02
County planning Official record

Per the Nov 2, 2026 DAPS report: Hunter Property (REZ2022-00019, data center height increase and substation, 195.69 acres) is suspended (on hold), and the Gainesville West and Gainesville East data center special use permits (SUP2023-00005 and -00006) are withdrawn. Gainesville East had a Planning Commission recommendation of denial on Dec 11, 2024.

Source: eservice.pwcgov.org ↗
2026-10-29
Community News report

Residents announced a petition asking the Board to defer data center applications that need discretionary approval (special use permits, rezonings, comprehensive plan amendments) for 12 months; it would not apply to by-right projects. The petition asks for time to update design standards and increase setbacks from homes, schools, parks and religious institutions (InsideNoVa, Oct 31). This is a petition by residents, not a Board action.

Source: insidenova.com ↗
2026-10-26
DEQ air permit Official record

DEQ's list of issued air permits for data centers shows registration 74118-4 (Article 6 - mNSR) issued 2026-10-26 to Cashvad Ventures LLC in Prince William County. The list gives no project size or status; the entry says nothing about whether the facility is built.

Source: deq.virginia.gov ↗
2026-10-22
Court ruling News report · Dominion Vint Hill substation expansion (SUP2025-00009), Prince William

Dominion Energy filed a 36-page suit in Prince William Circuit Court challenging the Board's denial of the Vint Hill substation permit as unlawful; it says the project is needed for regional grid reliability and load growth including data centers. The county told WTOP it does not comment on active litigation (WTOP, Oct 23).

Source: wtop.com ↗
2026-09-29
DEQ air permit Official record

DEQ's list of issued air permits for data centers shows registration 74342-2 (Article 6 - mNSR) issued 2026-09-29 to Amazon Data Services Inc IAD-110/111/112/113 in Prince William County. The list gives no project size or status; the entry says nothing about whether the facility is built.

Source: deq.virginia.gov ↗
2026-09-24
County planning Official record · Gardner Property data centers (REZ2023-00018, SUP2027-00008)

Special use permit application SUP2027-00008 for the Gardner Property data centers and substation was accepted, alongside the pending rezoning REZ2023-00018 (82.74 acres).

Source: eservice.pwcgov.org ↗
2026-09-22
Board of Supervisors News report · Dominion Vint Hill substation expansion (SUP2025-00009), Prince William

Board unanimously denied Dominion Energy's special use permit for the Vint Hill substation expansion (500 kV equipment, gas-insulated technology), citing proximity to homes and schools and transparency concerns (Prince William Times; WTOP).

Source: princewilliamtimes.com ↗
2026-09-22
Board of Supervisors Official record

Board adopted DPA2026-00006 (Ordinance 26-67) restructuring the Data Center Opportunity Zone Overlay District. Five eligibility pathways let properties already in the overlay remain; the overlay is closed to expansion; new data center proposals outside it in listed zoning districts must obtain a Special Use Permit (county planning office page).

Source: pwcva.gov ↗
2026-09-22
Board of Supervisors News report

The Board's 8-0 vote cut the overlay from 9,698 acres to 3,654 acres, about 62%, per a Planning Commission report cited by Bisnow; a motion to shorten the 90-day grace period to zero failed 5-3.

Source: bisnow.com ↗
2026-09-16
County planning News report · Atlantic Funding Development data centers (Dumfries Road)

Potomac Local's Sep 30 news links report county staff comments on the Atlantic Funding Development and Southgate South data center applications found substantial issues and gave applicants 45 days to revise, with no Planning Commission hearings scheduled.

Source: potomaclocal.com ↗
2026-09-01
Board of Supervisors Official record · Project Industry (REZ2025-00003)

Project Industry (REZ2025-00003) was set for a Board hearing on Sep 1, 2026 and is listed as deferred in the county's Nov 2, 2026 DAPS report.

Source: eservice.pwcgov.org ↗

Showing the 12 newest of 36 dated records. See all 38 on the Prince William County tracker page.

How we sourced this page

Virginia localities control data center siting mainly through zoning, so Board of Supervisors and City Council records are the main local decisions; DEQ permits and SCC dockets cover air emissions and power. Official sources are preferred over news, and company claims are attributed. Full methodology.

Frequently asked questions

How many data center projects does Prince William County have on record?

Virginia Data Center Watch tracks 13 projects in Prince William County (8 proposed / announced, 4 denied / withdrawn / canceled, 1 approved / permitted) and 38 dated public records, last verified 2026-11-02. Coverage is partial and a project missing here is not a statement that none exists.

What was the most recent recorded action in Prince William County?

2026-11-02: Pending per the Nov 2, 2026 DAPS report: Six Towers Industrial Park (REZ2026-00019, about 23.8 acres at Dumfries and Six Towers roads, up to about 518,649 sq ft of M-2 uses including data centers) and Manassas Corporate Center 8 (REZ2026-00032, about 23.25 acres for a data center). Source: eservice.pwcgov.org.

Where do the Prince William County records come from?

25 of 38 records link to a government source. Source sites used for Prince William County: bisnow.com, deq.virginia.gov, dominionenergy.com, eservice.pwcgov.org, insidenova.com, law.justia.com, loudoun.gov, potomaclocal.com, princewilliamtimes.com, protectpwc.org, pwcva.gov, virginiabusiness.com…. Each record shows its own label (official record, company claim, news report or third-party tracker).

How do I get alerts for Prince William County?

Sign up free for the Friday digest (1 locality, free for your first month). Same-day alerts for up to 5 localities start at $4/mo with a 30-day free trial.

Spot an error or a missing filing? Email [email protected] with the source link.

Free

Get the free weekly digest for your locality

Free weekly email every Friday for your first month, for 1 locality you pick: new board and council actions, permits, filings and hearings, plus the week's top Virginia changes. Every item links to its public source.

Want it same-day? Neighbor, $4/mo.