Dulles North Technology Park substation (appeal of Planning Commission denial)

B.F. Saul Company (applicant named by ZoneWire, not confirmed in a county document we opened)

Status
Planning Commission recommended denial and applicant appealed (Oct 2, 2026), Board hearing scheduled Nov 12, 2026
Developer / parties
B.F. Saul Company (applicant named by ZoneWire, not confirmed in a county document we opened)
Location
Route 28 corridor (Sterling District), Loudoun County
Size
Proposed substation of about 25 acres with a rezoning of about 1.69 acres, intended to serve the adjacent Dulles Technology Park data center plan (ZoneWire summary)
Reported benefits
Not stated in the sources we opened
Concerns / impacts
The Board denied a different Dulles-area substation on Sep 15 2026 (see Tech Park at Dulles substation), and the Loudoun Times notes that decision when reporting the Dulles Technology Park vote. The Planning Commission vote count comes from an aggregator and is not confirmed by a county document
Last verified
2026-11-02

Milestones

Figures are attributed in parentheses to the outlet or company that reported them. Where sources disagree, we show both.

  1. Sep 22 2026 Planning Commission recommended denial 4-3-1 (ZoneWire summary), Oct 2 2026 the applicant appealed the Commission's denial of the related commission permit, the Board hearing is on the Nov 12 2026 agenda and per the agenda packet the Board must act by Dec 1 2026 or the appeal is automatically denied (county eScribe agenda packet)

Related records

2026-09-22
County planning Third-party tracker Loudoun County · Dulles North Technology Park substation (appeal of Planning Commission denial)

Planning Commission recommended denial of the Dulles North Technology Park substation, 4-3-1 per ZoneWire (aggregator, not confirmed in a county document we opened). The applicant appealed the related commission permit denial on Oct 2, 2026.

Source: zonewire.co ↗

Sources

Found an error? Email [email protected] with a source link.

Free weekly digest

Email digest: not open yet

The free weekly email digest is not accepting signups yet, and we collect no email addresses on this site. Every locality and project page is free to read now.

Want it same-day? Neighbor, $4/mo.