Home / Stafford County / Project
Kings Corridor data center applications (Forest Lane, Simms Farm, Sisson North, Sisson South)
Real Estate Pursuits 2 LC (applicant/owner for all four, per county page)
- Status
- Under review; Planning Commission public hearing set for Nov 18, 2026 (postponed from Oct 14)
- Developer / parties
- Real Estate Pursuits 2 LC (applicant/owner for all four, per county page)
- Location
- George Washington District (Route 3 / Kings Highway), Stafford County
- Size
- County page: four applications on 1,404.82 acres, about 10.5 million sq ft of data centers in 37 buildings and 14 substations (Forest Lane 26 buildings/8 substations on 844.92 acres; Simms Farm 1 building/2 substations; Sisson South 10 buildings/1 substation; Sisson North is substation-only). WJLA described the proposal as over 1,500 acres
- Concerns / impacts
- WJLA interviewed residents whose homes adjoin all four sites and who said they oppose the plan (WJLA). The county page lists no benefit figures
- Last verified
- 2026-11-02
Milestones
- Applications deemed complete between Mar 26 and Jun 27, 2025
- staff reported to recommend denial of most of the applications (WJLA, Oct 2026)
- Oct 14 2026 Planning Commission meeting canceled and the hearing moved to Nov 18, 2026 6:00 p.m. in the Board Chambers by agreement of the applicant and staff to allow further review and refinement (Stafford County)
Related records
2026-11-18
County planning Official record
Upcoming: Planning Commission public hearing, 6:00 p.m. in the Board Chambers, on the Forest Lane, Simms Farm, Sisson North and Sisson South data center applications (Stafford County).
Source: staffordcountyva.gov ↗Sources
- Official record staffordcountyva.gov
- News report wjla.com