Home / Virginia guides / Loudoun County
Data centers in Loudoun County, Virginia: a source-linked guide
9 projects · 56 dated records · last verified 2026-11-02. Built only from records we have opened; every fact links to its source.
At a glance
- Projects tracked
- 9 (5 proposed / announced, 2 approved / permitted, 1 denied / withdrawn / canceled, 1 operational (any part))
- Dated records
- 56 (37 DEQ air permit; 11 Board of Supervisors; 4 County planning; 2 Utility regulator (SCC); 1 Community; 1 Court ruling)
- Official-source records
- 45 of 56
- Last verified
- 2026-11-02
Projects in Loudoun County
Amazon Web Services plan for the former GWU campus (Bridgefield / 'Project Potomac Promise'), Ashburn
Preliminary agreement to drop the data center use announced Oct 20, 2026, final agreements not yet complete
- Developer (as stated)
- Amazon Web Services (per county release and WTOP)
- Location
- Ashburn (Algonkian District)
- Size (as stated)
- About 122 acres bought by Amazon, with four data center buildings in the site plan (WTOP). Under the preliminary deal about 25 acres go to the county and the remaining 97 acres would be rezoned for housing and mixed use (county release)
- Investment (as stated)
- Amazon paid about $427 million for the campus in March 2026 (WTOP)
- Sources
- 2 linked (News report, Official record) · last verified 2026-11-02
- Mar 2026 Amazon bought the former George Washington University Virginia Science and Technology Campus (WTOP), Oct 20 2026 the Board voted to support a preliminary agreement under which Amazon intends to withdraw its data center application, the county release says the vote was unanimous while WTOP reports Supervisor Umstattd voted against the motion to fast-track the rezoning, so the vote count is conflicting, final agreements and zoning actions are still to come per the county release
Dulles Technology Park zoning conversion (data centers), Route 28 corridor, Sterling area
Planning Commission recommended denial (Sep 17, 2026), Board of Supervisors public hearing scheduled Nov 12, 2026
- Developer (as stated)
- Dulles Technology Park LLC / B.F. Saul Company (applicant named by ZoneWire, not confirmed in a county document we opened)
- Location
- Route 28 corridor (Sterling District)
- Size (as stated)
- Proposed: zoning conversion on 37.24 acres to allow about 979,000 sq ft of data centers (Loudoun Times quoting county documents), ZoneWire summary says three data center buildings and also describes the land as currently hotel and office uses
- Sources
- 3 linked (News report, Official record, Third-party tracker) · last verified 2026-11-02
- Sep 17 2026 Planning Commission recommended denial of the data center zoning conversion in a close vote (Loudoun Times headline, ZoneWire reports 5-4), the Board of Supervisors public hearing is on the Nov 12 2026 agenda (county eScribe agenda packet)
Dulles North Technology Park substation (appeal of Planning Commission denial)
Planning Commission recommended denial and applicant appealed (Oct 2, 2026), Board hearing scheduled Nov 12, 2026
- Developer (as stated)
- B.F. Saul Company (applicant named by ZoneWire, not confirmed in a county document we opened)
- Location
- Route 28 corridor (Sterling District)
- Size (as stated)
- Proposed substation of about 25 acres with a rezoning of about 1.69 acres, intended to serve the adjacent Dulles Technology Park data center plan (ZoneWire summary)
- Sources
- 3 linked (News report, Official record, Third-party tracker) · last verified 2026-11-02
- Sep 22 2026 Planning Commission recommended denial 4-3-1 (ZoneWire summary), Oct 2 2026 the applicant appealed the Commission's denial of the related commission permit, the Board hearing is on the Nov 12 2026 agenda and per the agenda packet the Board must act by Dec 1 2026 or the appeal is automatically denied (county eScribe agenda packet)
Golden Substation (Dominion Energy), Sterling
Board of Supervisors vote scheduled Nov 5, 2026
- Developer (as stated)
- Dominion Energy Virginia
- Location
- Sterling
- Size (as stated)
- Proposed electric substation, Dominion describes it as a reliability project (United Loudoun summary of the county record)
- Sources
- 3 linked (News report, Official record, Third-party tracker) · last verified 2026-11-02
- Jul 9 2026 Planning Commission recommended approval 6-1-2 (United Loudoun and ZoneWire summaries), Sep 1 2026 Board deferred the item to Dec 1 on a 5-4 vote (United Loudoun, citing Loudoun Now), Oct 20 2026 Board moved the vote up to Nov 5 on an 8-0-1 vote (county scheduling item and Loudoun Now), the Oct 20 Board item from Supervisor Saines ties the earlier vote to accelerating grid connection of Vantage VA2 from 2040 to 2028 (county agenda item and Loudoun Now)
Dominion 'Golden to Mars' 230/500 kV transmission line (SCC PUR-2025-00056)
Approved by the State Corporation Commission (final order Jun 29, 2026, Route 3A), appeal pending per United Loudoun
- Developer (as stated)
- Dominion Energy Virginia
- Location
- Loudoun County (Dulles area)
- Size (as stated)
- Per United Loudoun's summary of the SCC order: about 8.4 miles, in-service target Jun 1, 2028, estimated cost about $513 million (tracker summary, SCC order not opened)
- Sources
- 3 linked (News report, Official record, Third-party tracker) · last verified 2026-11-02
- SCC case PUR-2025-00056, Jun 29 2026 final order selecting Route 3A (county transmission page), the county page and United Loudoun name the affected loop differently (Lockridge vs Prentice), so that detail is conflicting
Dominion Aspen-Golden-Apollo-Twin Creeks 500 kV transmission line (Loudoun)
Approved by the SCC (Feb 2025) and affirmed by the Supreme Court of Virginia (Feb 19, 2026)
- Developer (as stated)
- Dominion Energy Virginia
- Location
- Loudoun County
- Size (as stated)
- Transmission line project in Loudoun County (county transmission page)
- Sources
- 2 linked (Official record) · last verified 2026-11-02
- Feb 2025 SCC approval (county transmission page), Feb 19 2026 Supreme Court of Virginia affirmed the SCC's decision (court opinion, record 250492)
Tech Park at Dulles substation (denied)
Denied by the Board of Supervisors, 6-3 (Sep 15, 2026)
- Developer (as stated)
- Not stated in the article we opened
- Location
- Near Washington Dulles International Airport
- Size (as stated)
- Proposed: a substation on about 20 acres of an 83-acre site south of Old Ox Road and west of Carter School Road, to power incoming data centers (Loudoun Now)
- Sources
- 2 linked (News report) · last verified 2026-11-02
- Sep 15 2026 Board denied the application 6-3 (Loudoun Now)
Yondr Tarring data center special exception
Application under review, no Planning Commission or Board hearing date found
- Developer (as stated)
- Yondr
- Location
- Loudoun County
- Size (as stated)
- Special exception application for a data center (United Loudoun tracker)
- Sources
- 2 linked (Official record, Third-party tracker) · last verified 2026-11-02
- Nov 2025 application filed under LEGI-2025-0049 (United Loudoun tracker), Apr 2026 a minor additional special exception was filed (United Loudoun tracker), the county reports 33 active legislative applications for data centers and related substations as of Oct 2026 (county agenda packet)
Vantage VA2 data center on gas turbines, Sterling
Operational (on-site gas turbines) with Dominion grid connection pending
- Developer (as stated)
- Vantage Data Centers
- Location
- Sterling (Glenn Drive)
- Size (as stated)
- Existing data center along Glenn Drive in Sterling, described as the only data center in Virginia operating on on-site natural gas turbines (Loudoun Now)
- Sources
- 2 linked (News report, Official record) · last verified 2026-11-02
- Aug 2026 community town hall on turbine noise (Loudoun Now), Oct 20 2026 a Board item from Supervisor Saines says he worked with Dominion and Vantage to accelerate VA2 grid interconnection from 2040 to 2028 and ties it to advancing the Golden Substation vote (county agenda item), Oct 21 2026 Loudoun Now reports Dominion and Vantage agreed to a temporary bridging arrangement that would supply part of the campus power by the end of 2028 so the turbines can be removed, Dominion says this does not move VA2 ahead in the large-load queue.
Upcoming hearings and deadlines
Upcoming: Board of Supervisors business meeting scheduled to act on the Golden Substation application (LEGI-2025-0012, SPEX-2025-0032, -0033 and -0137).
Source: pub-loudoun.escribemeetings.com ↗Upcoming: Board of Supervisors public hearing on the Dulles Technology Park zoning conversion and the appeal of the Planning Commission's denial for the Dulles North Technology Park substation. Per the agenda packet the Board must act on the appeal by Dec 1, 2026 or it is automatically denied.
Source: pub-loudoun.escribemeetings.com ↗Upcoming: SCC evidentiary hearing begins on Dominion's Morrisville-Wishing Star 500 kV line (PUR-2026-00021), per Dominion's project page.
Source: dominionenergy.com ↗Upcoming: Board scheduled to take up agenda item 14p, the resolution to pause consideration of legislative data center and substation applications. The pause would not take effect unless the Board adopts the resolution (DataCenterFeed, citing the county). Date per DataCenterFeed; confirm on the Board agenda.
Source: datacenterfeed.com ↗Timeline of dated records
Agenda item 14p, a resolution to pause Board consideration of legislative applications for data centers and substations for up to 12 months (effective date written as Sept 15, 2026), was removed from the Oct 20 business meeting agenda and deferred to Nov 17 to give the County Attorney time for more legal and fiscal analysis (Loudoun Now; county agenda item description).
Source: loudounnow.com ↗Board voted to support a preliminary agreement with Amazon Web Services under which Amazon intends to withdraw its data center application on the former GWU campus in Ashburn. The county release describes the vote as unanimous, WTOP reports Supervisor Umstattd opposed a motion to fast-track the rezoning, so the vote count is conflicting. Terms are preliminary, final agreements are still pending.
Source: loudoun.gov ↗Board voted 8-0-1 (Supervisor Briskman absent) to move the Golden Substation vote from Dec 1 to Nov 5, 2026, on a motion from Supervisor Saines tying it to an agreement among Dominion, Vantage and the Sterling district office to speed grid connection of Vantage VA2 from 2040 to 2028.
Source: loudounnow.com ↗County staff item on pending legislative applications reports 33 active applications for data centers and related substations (10 data centers, 12 non-reliability substations, 1 grid-reliability-only substation and 10 combined data center and substation). The agenda item addressed whether to pause them. Figures are as stated in the agenda packet.
Source: pub-loudoun.escribemeetings.com ↗Board tabled, without a vote, a proposal to end grandfathering for pending data center projects and a companion motion for an outside audit of them. Bisnow reports 15 projects totaling about 10.5 million sq ft in 30 buildings are advancing under the legacy exemption; FOX 5 DC reports the County Attorney warned that ending grandfathering could cost the county up to $60 million in litigation (figures differ from the county's Sept 16 release, which cited at least 17 cases).
Source: bisnow.com ↗Scheduled: Board was set to receive County Attorney legal analysis on whether the 2025 grandfathering exceptions for pending administrative data center applications can be ended (per the Sept 16 release, which says at least 17 land use cases covering more than 11 million sq ft are grandfathered). [Unverified: the outcome of the Oct 6 item was not found.]
Source: loudoun.gov ↗DEQ's list of issued air permits for data centers shows registration 74321-2 (Article 6 - mNSR) issued 2026-09-28 to Belmont Innovation Campus in Loudoun County. The list gives no project size or status; the entry says nothing about whether the facility is built.
Source: deq.virginia.gov ↗Planning Commission recommended denial of the Dulles North Technology Park substation, 4-3-1 per ZoneWire (aggregator, not confirmed in a county document we opened). The applicant appealed the related commission permit denial on Oct 2, 2026.
Source: zonewire.co ↗Planning Commission recommended denial of the Dulles Technology Park zoning conversion (about 979,000 sq ft of data centers on 37.24 acres) in a close vote. The Loudoun Times calls it close, ZoneWire reports 5-4. A different ZoneWire page describes a Dulles Technology Park item as approved, which conflicts with this report and is treated as unreliable.
Source: loudountimes.com ↗Board voted 7-1-1 to pause Board consideration of certain legislative applications for data centers and substations, advancing a proposal from Supervisor Briskman; a separate 7-1-1 vote approved an exception for 'grid reliability' substations. Per the Supervisor's Sept 16 release hosted on loudoun.gov, the pause takes effect immediately; County Attorney advised a blanket moratorium is not allowed. Later coverage says the formal resolution had not yet been adopted (see Oct 20 record), so whether the pause is in force is described differently by different sources.
Source: loudoun.gov ↗Board denied, 6-3, a substation application near Washington Dulles International Airport (Tech Park at Dulles) that would have powered incoming data centers, on about 20 acres of an 83-acre site south of Old Ox Road.
Source: loudounnow.com ↗Supervisor Saines held a town hall on noise and emissions from the on-site gas turbines at the Vantage VA2 data center in Sterling. Loudoun Now reports it is the only data center in Virginia running on on-site gas turbines.
Source: loudounnow.com ↗How we sourced this page
Virginia localities control data center siting mainly through zoning, so Board of Supervisors and City Council records are the main local decisions; DEQ permits and SCC dockets cover air emissions and power. Official sources are preferred over news, and company claims are attributed. Full methodology.
Frequently asked questions
How many data center projects does Loudoun County have on record?
Virginia Data Center Watch tracks 9 projects in Loudoun County (5 proposed / announced, 2 approved / permitted, 1 denied / withdrawn / canceled, 1 operational (any part)) and 56 dated public records, last verified 2026-11-02. Coverage is partial and a project missing here is not a statement that none exists.
What was the most recent recorded action in Loudoun County?
2026-10-20: Agenda item 14p, a resolution to pause Board consideration of legislative applications for data centers and substations for up to 12 months (effective date written as Sept 15, 2026), was removed from the Oct 20 business meeting agenda and deferred to Nov 17 to give the County Attorney time for more… Source: loudounnow.com.
Where do the Loudoun County records come from?
45 of 56 records link to a government source. Source sites used for Loudoun County: bisnow.com, datacenterfeed.com, deq.virginia.gov, dominionenergy.com, loudoun.gov, loudounnow.com, loudountimes.com, pub-loudoun.escribemeetings.com, unitedloudoun.org, vacourts.gov, wtop.com, zonewire.co. Each record shows its own label (official record, company claim, news report or third-party tracker).
How do I get alerts for Loudoun County?
Sign up free for the Friday digest (1 locality, free for your first month). Same-day alerts for up to 5 localities start at $4/mo with a 30-day free trial.
Free
Get the free weekly digest for your locality
Free weekly email every Friday for your first month, for 1 locality you pick: new board and council actions, permits, filings and hearings, plus the week's top Virginia changes. Every item links to its public source.
Want it same-day? Neighbor, $4/mo.