Coverage is partial: we are adding localities as we verify records. A missing locality does not mean it has no data center activity.

Home / Virginia guides / Stafford County

Data centers in Stafford County, Virginia: a source-linked guide

2 projects · 3 dated records · last verified 2026-11-02. Built only from records we have opened; every fact links to its source.

Live tracker: projects and dated records for Stafford County. This page is the long-form guide.

At a glance

Projects tracked
2 (1 approved / permitted, 1 proposed / announced)
Dated records
3 (1 County planning; 1 Board of Supervisors; 1 DEQ air permit)
Official-source records
2 of 3
Last verified
2026-11-02

Projects in Stafford County

Accokeek Center data campus

Rezoning and substation CUP approved 4-3 (Oct 7, 2026)

Developer (as stated)
Applicant not named in the source article
Size (as stated)
Two data center buildings, up to two stories, totaling 590,000 sq ft, plus an electrical substation, on about 121 acres west of Richmond Highway (Route 1) in the Falmouth District (county staff report, per Potomac Local)
Sources
3 linked (News report) · last verified 2026-11-02
  • Aug 26 2026 Planning Commission hearing
  • Oct 7 2026 Board of Supervisors voted 5-2 against a motion to delay to Oct 20, then approved ordinance O26-16 (rezoning from agricultural, rural residential and office to M-2 heavy industrial, with proffers revised that night) 4-3, and resolution R26-128 (conditional use permit for an electrical substation) 4-3 (Potomac Local). The meeting ran from 5 p.m. to after 1 a.m.
  • Supervisor Vanuch's request to continue it failed, and Chairman Diggs said the county ordinance allows a smaller setback when impacts are mitigated (Fredericksburg Free Press)

Kings Corridor data center applications (Forest Lane, Simms Farm, Sisson North, Sisson South)

Under review; Planning Commission public hearing set for Nov 18, 2026 (postponed from Oct 14)

Developer (as stated)
Real Estate Pursuits 2 LC (applicant/owner for all four, per county page)
Location
George Washington District (Route 3 / Kings Highway)
Size (as stated)
County page: four applications on 1,404.82 acres, about 10.5 million sq ft of data centers in 37 buildings and 14 substations (Forest Lane 26 buildings/8 substations on 844.92 acres; Simms Farm 1 building/2 substations; Sisson South 10 buildings/1 substation; Sisson North is substation-only). WJLA described the proposal as over 1,500 acres
Sources
2 linked (News report, Official record) · last verified 2026-11-02
  • Applications deemed complete between Mar 26 and Jun 27, 2025
  • staff reported to recommend denial of most of the applications (WJLA, Oct 2026)
  • Oct 14 2026 Planning Commission meeting canceled and the hearing moved to Nov 18, 2026 6:00 p.m. in the Board Chambers by agreement of the applicant and staff to allow further review and refinement (Stafford County)

Upcoming hearings and deadlines

2026-11-18
County planning Official record · Kings Corridor data center applications (Forest Lane, Simms Farm, Sisson North, Sisson South)

Upcoming: Planning Commission public hearing, 6:00 p.m. in the Board Chambers, on the Forest Lane, Simms Farm, Sisson North and Sisson South data center applications (Stafford County).

Source: staffordcountyva.gov ↗

Timeline of dated records

2026-10-07
Board of Supervisors News report · Accokeek Center data campus

Board approved the Accokeek Center data campus rezoning (ordinance O26-16, to M-2 heavy industrial) 4-3 and the related electrical substation conditional use permit (R26-128) 4-3; two buildings totaling 590,000 sq ft on about 121 acres in the Falmouth District. A motion to delay to Oct 20 failed 5-2 (Potomac Local).

Source: potomaclocal.com ↗
2026-05-12
DEQ air permit Official record

DEQ's list of issued air permits for data centers shows registration 74338-1 (Article 6 - mNSR) issued 2026-05-12 to Vantage Data Centers VA41 LLC in Stafford County. The list gives no project size or status; the entry says nothing about whether the facility is built.

Source: deq.virginia.gov ↗

How we sourced this page

Virginia localities control data center siting mainly through zoning, so Board of Supervisors and City Council records are the main local decisions; DEQ permits and SCC dockets cover air emissions and power. Official sources are preferred over news, and company claims are attributed. Full methodology.

Frequently asked questions

How many data center projects does Stafford County have on record?

Virginia Data Center Watch tracks 2 projects in Stafford County (1 approved / permitted, 1 proposed / announced) and 3 dated public records, last verified 2026-11-02. Coverage is partial and a project missing here is not a statement that none exists.

What was the most recent recorded action in Stafford County?

2026-10-07: Board approved the Accokeek Center data campus rezoning (ordinance O26-16, to M-2 heavy industrial) 4-3 and the related electrical substation conditional use permit (R26-128) 4-3; two buildings totaling 590,000 sq ft on about 121 acres in the Falmouth District. Source: potomaclocal.com.

Where do the Stafford County records come from?

2 of 3 records link to a government source. Source sites used for Stafford County: deq.virginia.gov, fredericksburgfreepress.com, potomaclocal.com, savestafford.org, staffordcountyva.gov, wjla.com. Each record shows its own label (official record, company claim, news report or third-party tracker).

How do I get alerts for Stafford County?

Sign up free for the Friday digest (1 locality, free for your first month). Same-day alerts for up to 5 localities start at $4/mo with a 30-day free trial.

Spot an error or a missing filing? Email [email protected] with the source link.

Free

Get the free weekly digest for your locality

Free weekly email every Friday for your first month, for 1 locality you pick: new board and council actions, permits, filings and hearings, plus the week's top Virginia changes. Every item links to its public source.

Want it same-day? Neighbor, $4/mo.